BetaActiveBatteryPJMLBNL + Live
150 MW storage in City Of Virginia Beach, VA · In queue since February 2023 · Proposed COD December 2023
150 MW
Capacity
1
Components
Battery
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
10 months
Schedule
27 months past proposed COD
In Study38%
Queue EntryFeb 1, 2023
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
VA
County
City Of Virginia Beach
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Oceana 230kV
Data Source
LBNL + Live
No news available for this project.