— Project Summary

Queue ID
PJM-AI2-037
Capacity
142 MW
Technology
Solar
Status
active
Location
King And Queen, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

142 MW generation in King And Queen, VA · In queue since January 2023 · Proposed COD December 2027

142 MW

Capacity

1

Components

Solar

3y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 11m

In Study38%
Queue EntryJan 25, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

VA

County

King And Queen

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Lauraville-Dunbrooke 115kV

Data Source

LBNL + Live

No news available for this project.