BetaActiveSolarPJMLBNL + Live
70 MW generation in Union, OH · In queue since December 2022 · Proposed COD December 2026
70 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4 years
In Study38%
Queue EntryDec 31, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-20
Project Details
State
OH
County
Union
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Clarksburg - Biers Run 69 kV
Data Source
LBNL + Live
No news available for this project.