BetaActiveOtherPJMLBNL + Live
10 MW generation in New Castle, DE · In queue since December 2022 · Proposed COD October 2026
10 MW
Capacity
1
Components
Other
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 10m
In Study38%
Queue EntryDec 23, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-31
Project Details
State
DE
County
New Castle
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Data Source
LBNL + Live
No news available for this project.