— Project Summary

Queue ID
PJM-AI2-025
Capacity
10 MW
Technology
Other
Status
active
Location
New Castle, DE
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveOtherPJMLBNL + Live

10 MW generation in New Castle, DE · In queue since December 2022 · Proposed COD October 2026

10 MW

Capacity

1

Components

Other

3y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 10m

In Study38%
Queue EntryDec 23, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-10-31

Project Details

State

DE

County

New Castle

Region

PJM

Developer

Utility

DPL

Entity

PJM

Data Source

LBNL + Live