BetaActiveSolarPJMLBNL + Live
60 MW generation in Meigs, OH · In queue since December 2022 · Proposed COD December 2028
60 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6 years
In Study38%
Queue EntryDec 22, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
OH
County
Meigs
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Racine - Ravenswood 69kV
Data Source
LBNL + Live
No news available for this project.