— Project Summary

Queue ID
PJM-AI2-024
Capacity
60 MW
Technology
Solar
Status
active
Location
Meigs, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

60 MW generation in Meigs, OH · In queue since December 2022 · Proposed COD December 2028

60 MW

Capacity

1

Components

Solar

3y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6 years

In Study38%
Queue EntryDec 22, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

OH

County

Meigs

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Racine - Ravenswood 69kV

Data Source

LBNL + Live

No news available for this project.