BetaActiveGasPJMLBNL + Live
60 MW generation in Bradford, PA · In queue since December 2022 · Proposed COD May 2025
60 MW
Capacity
1
Components
Gas
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 5m
Schedule
11 months past proposed COD
In Study38%
Queue EntryDec 20, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-05-01
Project Details
State
PA
County
Bradford
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
East Towanda 230 kV
Data Source
LBNL + Live
No news available for this project.