BetaActiveGasPJMLBNL + Live
19 MW generation in Warren, VA · In queue since December 2022 · Proposed COD December 2022
19 MW
Capacity
1
Components
Gas
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
<1 month
Schedule
39 months past proposed COD
In Study38%
Queue EntryDec 10, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
VA
County
Warren
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Warren County 500 kV
Data Source
LBNL + Live
No news available for this project.