— Project Summary

Queue ID
PJM-AI2-020
Capacity
19 MW
Technology
Gas
Status
active
Location
Warren, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveGasPJMLBNL + Live

19 MW generation in Warren, VA · In queue since December 2022 · Proposed COD December 2022

19 MW

Capacity

1

Components

Gas

3y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

<1 month

Schedule

39 months past proposed COD

In Study38%
Queue EntryDec 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-31

Project Details

State

VA

County

Warren

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Warren County 500 kV

Data Source

LBNL + Live

No news available for this project.