BetaActiveSolarPJMLBNL + Live
4 MW generation in Somerset, PA · In queue since December 2022 · Proposed COD December 2026
4 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4 years
In Study38%
Queue EntryDec 9, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
PA
County
Somerset
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
TBD 23 kV
Data Source
LBNL + Live
No news available for this project.