— Project Summary

Queue ID
PJM-AI2-014
Capacity
37.9 MW
Technology
Solar
Status
active
Location
Kankakee, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

37.9 MW generation in Kankakee, IL · In queue since November 2022 · Proposed COD May 2026

37.9 MW

Capacity

1

Components

Solar

3y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 6m

In Study38%
Queue EntryNov 30, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-05-29

Project Details

State

IL

County

Kankakee

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Kankakee 138 kV

Data Source

LBNL + Live

No news available for this project.