— Project Summary

Queue ID
PJM-AI2-007
Capacity
40 MW
Technology
Battery
Status
active
Location
Kane, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

40 MW storage in Kane, IL · In queue since November 2022 · Proposed COD June 2027

40 MW

Capacity

1

Components

Battery

3y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 7m

In Study38%
Queue EntryNov 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

IL

County

Kane

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Rocky Road 138kV

Data Source

LBNL + Live

No news available for this project.