BetaActiveSolarBatteryPJMLBNL + Live
20 MW hybrid in Centre, PA · In queue since September 2022 · Proposed COD June 2024
20 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 9m
Schedule
21 months past proposed COD
In Study38%
Queue EntrySep 10, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-30
Project Details
State
PA
County
Centre
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Philipsburg 115 kV V
Data Source
LBNL + Live
No news available for this project.