— Project Summary

Queue ID
PJM-AI1-211
Capacity
68 MW
Technology
Solar+Battery
Status
active
Location
Preston, WV
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL + Live

68 MW hybrid in Preston, WV · In queue since September 2022 · Proposed COD December 2024

68 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 3m

Schedule

15 months past proposed COD

In Study38%
Queue EntrySep 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

WV

County

Preston

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Brandonville - Necessity 138 kV

Data Source

LBNL + Live

No news available for this project.