— Project Summary

Queue ID
PJM-AI1-173
Capacity
16 MW
Technology
Solar
Status
active
Location
Stephenson, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

16 MW generation in Stephenson, IL · In queue since September 2022 · Proposed COD April 2027

16 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 7m

In Study38%
Queue EntrySep 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-30

Project Details

State

IL

County

Stephenson

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Lena - Freeport 34.5 kV

Data Source

LBNL + Live

No news available for this project.