BetaActiveSolarBatteryPJMLBNL + Live
250 MW hybrid in Grundy, IL · In queue since September 2022 · Proposed COD April 2028
250 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 7m
In Study38%
Queue EntrySep 10, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-30
Project Details
State
IL
County
Grundy
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Katydid Road - Goodings Grove 345 kV
Data Source
LBNL + Live
No news available for this project.