BetaActiveSolarBatteryPJMLBNL + Live
100 MW hybrid in Dekalb, IL · In queue since September 2022 · Proposed COD October 2027
100 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 1m
In Study38%
Queue EntrySep 10, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-31
Project Details
State
IL
County
Dekalb
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Glidden - Sugar Grove 138kV
Data Source
LBNL + Live
No news available for this project.