— Project Summary

Queue ID
PJM-AI1-167
Capacity
250 MW
Technology
Battery
Status
active
Location
Clermont, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

250 MW storage in Clermont, OH · In queue since September 2022 · Proposed COD December 2028

250 MW

Capacity

1

Components

Battery

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6y 3m

In Study38%
Queue EntrySep 9, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

OH

County

Clermont

Region

PJM

Developer

Utility

DEOK

Entity

PJM

Point of Interconnection

Cedarville 138 kV

Data Source

LBNL + Live

No news available for this project.