BetaActiveSolarPJMLBNL + Live
1.4 MW generation in Crawford, PA · In queue since September 2022 · Proposed COD January 2028
1.4 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 4m
In Study38%
Queue EntrySep 9, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-01
Project Details
State
PA
County
Crawford
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Crawford Solar 3 34.5 kV
Data Source
LBNL + Live
No news available for this project.