— Project Summary

Queue ID
PJM-AI1-154
Capacity
230 MW
Technology
Battery
Status
active
Location
Will, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

230 MW storage in Will, IL · In queue since September 2022 · Proposed COD January 2027

230 MW

Capacity

1

Components

Battery

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 4m

In Study38%
Queue EntrySep 9, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-04

Project Details

State

IL

County

Will

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Goodings Grove 138 kV

Data Source

LBNL + Live

No news available for this project.