— Project Summary

Queue ID
PJM-AI1-152
Capacity
19.9 MW
Technology
Solar+Battery
Status
active
Location
Northampton, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL + Live

19.9 MW hybrid in Northampton, PA · In queue since September 2022 · Proposed COD January 2027

19.9 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 4m

In Study38%
Queue EntrySep 9, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-04

Project Details

State

PA

County

Northampton

Region

PJM

Developer

Utility

ME

Entity

PJM

Point of Interconnection

Siegfried - Nazareth 69 kV

Data Source

LBNL + Live

No news available for this project.