— Project Summary

Queue ID
PJM-AI1-149
Capacity
250 MW
Technology
Battery
Status
active
Location
Mchenry, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

250 MW storage in Mchenry, IL · In queue since September 2022 · Proposed COD July 2025

250 MW

Capacity

1

Components

Battery

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 10m

Schedule

9 months past proposed COD

In Study38%
Queue EntrySep 9, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-07-01

Project Details

State

IL

County

Mchenry

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Pleasant Valley 345 kV

Data Source

LBNL + Live

No news available for this project.