BetaActiveSolarPJMLBNL + Live
125 MW generation in Prince Edward, VA · In queue since September 2022 · Proposed COD September 2026
125 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4 years
In Study38%
Queue EntrySep 9, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-30
Project Details
State
VA
County
Prince Edward
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Farmville - Moran DP 115 kV
Data Source
LBNL + Live
No news available for this project.