— Project Summary

Queue ID
PJM-AI1-137
Capacity
155 MW
Technology
Solar
Status
active
Location
Warren, NJ
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

155 MW generation in Warren, NJ · In queue since September 2022 · Proposed COD September 2025

155 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3 years

Schedule

6 months past proposed COD

In Study38%
Queue EntrySep 9, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-29

Project Details

State

NJ

County

Warren

Region

PJM

Developer

Utility

JCPL

Entity

PJM

Point of Interconnection

Greystone - Portland 230 kV

Data Source

LBNL + Live

No news available for this project.