BetaActiveSolarBatteryPJMLBNL + Live
50 MW hybrid in Fleming, KY · In queue since September 2022 · Proposed COD April 2029
50 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 7m
In Study38%
Queue EntrySep 8, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-30
Project Details
State
KY
County
Fleming
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Hillsboro 69 kV
Data Source
LBNL + Live
No news available for this project.