— Project Summary

Queue ID
PJM-AI1-123
Capacity
59 MW
Technology
Solar
Status
active
Location
Lunenburg, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

59 MW generation in Lunenburg, VA · In queue since September 2022 · Proposed COD September 2026

59 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4 years

In Study38%
Queue EntrySep 8, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-30

Project Details

State

VA

County

Lunenburg

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Nutbush-Victoria DP 115kV

Data Source

LBNL + Live

No news available for this project.