51.6 MW generation in Warren, NJ · In queue since September 2022 · Proposed COD September 2025
51.6 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3 years
Schedule
6 months past proposed COD
In Study38%
Queue EntrySep 7, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-29
Project Details
State
NJ
County
Warren
Region
PJM
Developer
—
Utility
JCPL
Entity
PJM
Point of Interconnection
Pequest River - Gilbert 115 kV
Data Source
LBNL + Live