BetaActiveOffshore WindPJMLBNL + Live
1,310 MW generation in Middlesex, NJ · In queue since September 2022 · Proposed COD December 2029
1,310 MW
Capacity
1
Components
Offshore Wind
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
7y 3m
In Study38%
Queue EntrySep 1, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
NJ
County
Middlesex
Region
PJM
Developer
—
Utility
PSEG
Entity
PJM
Point of Interconnection
Deans 500 kV
Data Source
LBNL + Live
No news available for this project.