— Project Summary

Queue ID
PJM-AI1-101
Capacity
100 MW
Technology
Solar
Status
active
Location
Lackawanna, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

100 MW generation in Lackawanna, PA · In queue since August 2022 · Proposed COD September 2029

100 MW

Capacity

1

Components

Solar

3y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

7y 1m

In Study38%
Queue EntryAug 30, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-01

Project Details

State

PA

County

Lackawanna

Region

PJM

Developer

Utility

PPL

Entity

PJM

Point of Interconnection

Pocono-Acahela 230 kV

Data Source

LBNL + Live

No news available for this project.