BetaActiveSolarPJMLBNL + Live
100 MW generation in Lackawanna, PA · In queue since August 2022 · Proposed COD September 2029
100 MW
Capacity
1
Components
Solar
3y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
7y 1m
In Study38%
Queue EntryAug 30, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-01
Project Details
State
PA
County
Lackawanna
Region
PJM
Developer
—
Utility
PPL
Entity
PJM
Point of Interconnection
Pocono-Acahela 230 kV
Data Source
LBNL + Live
No news available for this project.