BetaActiveSolarPJMLBNL + Live
49.9 MW generation in Seneca, OH · In queue since August 2022 · Proposed COD July 2025
49.9 MW
Capacity
1
Components
Solar
3y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 11m
Schedule
9 months past proposed COD
In Study38%
Queue EntryAug 4, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-07-01
Project Details
State
OH
County
Seneca
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Bascom 69 kV
Data Source
LBNL + Live
No news available for this project.