BetaActiveBatteryPJMLBNL + Live
100 MW storage in City Of Suffolk, VA · In queue since July 2022 · Proposed COD September 2025
100 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 2m
Schedule
7 months past proposed COD
In Study38%
Queue EntryJul 29, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-01
Project Details
State
VA
County
City Of Suffolk
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Myrtle - Oak Ridge 115 kV
Data Source
LBNL + Live