BetaActiveBatteryPJMLBNL + Live
50 MW storage in Prince George, VA · In queue since July 2022 · Proposed COD September 2025
50 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 2m
Schedule
7 months past proposed COD
In Study38%
Queue EntryJul 29, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-01
Project Details
State
VA
County
Prince George
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Poe- New Bohemia 115kV
Data Source
LBNL + Live
No news available for this project.