— Project Summary

Queue ID
PJM-AI1-088
Capacity
50 MW
Technology
Battery
Status
active
Location
Prince George, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

50 MW storage in Prince George, VA · In queue since July 2022 · Proposed COD September 2025

50 MW

Capacity

1

Components

Battery

3y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 2m

Schedule

7 months past proposed COD

In Study38%
Queue EntryJul 29, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-01

Project Details

State

VA

County

Prince George

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Poe- New Bohemia 115kV

Data Source

LBNL + Live