BetaActiveSolarPJMLBNL + Live
15.75 MW generation in Mchenry, IL · In queue since July 2022 · Proposed COD October 2025
15.75 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 3m
Schedule
6 months past proposed COD
In Study38%
Queue EntryJul 15, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-01
Project Details
State
IL
County
Mchenry
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Marengo 34.5 kV Line
Data Source
LBNL + Live
No news available for this project.