BetaActiveSolarPJMLBNL + Live
19.8 MW generation in Delaware, PA · In queue since July 2022 · Proposed COD June 2024
19.8 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 11m
Schedule
21 months past proposed COD
In Study38%
Queue EntryJul 11, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-30
Project Details
State
PA
County
Delaware
Region
PJM
Developer
—
Utility
PECO
Entity
PJM
Point of Interconnection
TBD 13.2 kV
Data Source
LBNL + Live
No news available for this project.