— Project Summary

Queue ID
PJM-AI1-053
Capacity
6.6 MW
Technology
Solar
Status
active
Location
Mercer, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarDieselPJMLBNL + Live

6.6 MW hybrid in Mercer, PA · In queue since June 2022 · Proposed COD December 2022

6.6 MW

Capacity

1

Components

Solar

3y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

6 months

Schedule

40 months past proposed COD

In Study38%
Queue EntryJun 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-01

Project Details

State

PA

County

Mercer

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

McDowell - Campbell 69 kV

Data Source

LBNL + Live

No news available for this project.