— Project Summary

Queue ID
PJM-AI1-039
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Clearfield, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL + Live

200 MW hybrid in Clearfield, PA · In queue since April 2022 · Proposed COD June 2025

200 MW

Capacity

1

Components

Solar

3y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 2m

Schedule

9 months past proposed COD

In Study38%
Queue EntryApr 19, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-30

Project Details

State

PA

County

Clearfield

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Moshannon-Milesburg 230 kV VIII

Data Source

LBNL + Live