BetaActiveSolarBatteryPJMLBNL + Live
200 MW hybrid in Clearfield, PA · In queue since April 2022 · Proposed COD June 2025
200 MW
Capacity
1
Components
Solar
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 2m
Schedule
9 months past proposed COD
In Study38%
Queue EntryApr 19, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-30
Project Details
State
PA
County
Clearfield
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Moshannon-Milesburg 230 kV VIII
Data Source
LBNL + Live
No news available for this project.