95.76 MW generation in Carbon, PA · In queue since April 2022 · Proposed COD March 2024
95.76 MW
Capacity
1
Components
Solar
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 11m
Schedule
24 months past proposed COD
In Study38%
Queue EntryApr 12, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-03-31
Project Details
State
PA
County
Carbon
Region
PJM
Developer
—
Utility
PPL
Entity
PJM
Point of Interconnection
Harwood-Siegfried 230kV II
Data Source
LBNL + Live