BetaActiveSolarPJMLBNL + Live
5 MW generation in Erie, PA · In queue since April 2022 · Proposed COD December 2024
5 MW
Capacity
1
Components
Solar
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 8m
Schedule
16 months past proposed COD
In Study38%
Queue EntryApr 1, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-13
Project Details
State
PA
County
Erie
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Corry East - Garland Jct 34.5 kV
Data Source
LBNL + Live