BetaActiveSolarPJMLBNL + Live
5 MW generation in — · In queue since April 2022 · Proposed COD November 2023
5 MW
Capacity
1
Components
Solar
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 7m
Schedule
29 months past proposed COD
In Study38%
Queue EntryApr 2, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-11-01
Project Details
State
—
County
—
Region
PJM
Developer
—
Utility
PPL
Entity
PJM
Point of Interconnection
Ringtown 12 kV
Data Source
LBNL + Live
No news available for this project.