— Project Summary

Queue ID
PJM-AI1-020
Capacity
1.98 MW
Technology
Solar
Status
active
Location
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

1.98 MW generation in · In queue since April 2022 · Proposed COD March 2023

1.98 MW

Capacity

1

Components

Solar

3y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

11 months

Schedule

36 months past proposed COD

In Study38%
Queue EntryApr 2, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-03-31

Project Details

State

County

Region

PJM

Developer

Utility

DPL

Entity

PJM

Point of Interconnection

TBD

Data Source

LBNL + Live

No news available for this project.