BetaActiveBatteryPJMLBNL + Live
200 MW storage in Charles City, VA · In queue since April 2022 · Proposed COD December 2026
200 MW
Capacity
1
Components
Battery
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 8m
In Study38%
Queue EntryApr 1, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
VA
County
Charles City
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Chickahominy 230 kV
Data Source
LBNL + Live
No news available for this project.