— Project Summary

Queue ID
PJM-AI1-001
Capacity
2100 MW
Technology
Offshore Wind
Status
active
Location
Monmouth, NJ
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveOffshore WindPJMLBNL + Live

2,100 MW generation in Monmouth, NJ · In queue since April 2022 · Proposed COD October 2029

2,100 MW

Capacity

1

Components

Offshore Wind

3y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

7y 6m

In Study38%
Queue EntryApr 2, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-10-10

Project Details

State

NJ

County

Monmouth

Region

PJM

Developer

Utility

JCPL

Entity

PJM

Point of Interconnection

Larrabee 230 kV

Data Source

LBNL + Live