BetaActiveSolarBatteryPJMLBNL + Live
30 MW hybrid in KY · In queue since March 2022 · Proposed COD June 2025
30 MW
Capacity
1
Components
Solar
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 3m
Schedule
10 months past proposed COD
In Study38%
Queue EntryMar 10, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
KY
County
—
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
New Castle 69 kV
Data Source
LBNL + Live
No news available for this project.