— Project Summary

Queue ID
PJM-AH2-399
Capacity
20 MW
Technology
Solar
Status
active
Location
Rockingham, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

20 MW generation in Rockingham, VA · In queue since March 2022 · Proposed COD October 2026

20 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 7m

In Study38%
Queue EntryMar 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-10-01

Project Details

State

VA

County

Rockingham

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

TBD 34.5kV

Data Source

LBNL + Live

No news available for this project.