— Project Summary

Queue ID
PJM-AH2-395
Capacity
2.31 MW
Technology
Battery
Status
active
Location
Lawrence, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

2.31 MW storage in Lawrence, PA · In queue since March 2022 · Proposed COD December 2023

2.31 MW

Capacity

1

Components

Battery

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

1y 9m

Schedule

27 months past proposed COD

In Study38%
Queue EntryMar 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-29

Project Details

State

PA

County

Lawrence

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

Walters Karl 69 kV II

Data Source

LBNL + Live

No news available for this project.