BetaActiveWindPJMLBNL + Live
191.5 MW generation in Pendleton, WV · In queue since March 2022 · Proposed COD July 2027
191.5 MW
Capacity
1
Components
Wind
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 4m
In Study38%
Queue EntryMar 10, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-30
Project Details
State
WV
County
Pendleton
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
North Franklin 138 kV
Data Source
LBNL + Live
No news available for this project.