— Project Summary

Queue ID
PJM-AH2-383
Capacity
70 MW
Technology
Solar+Battery
Status
active
Location
Fleming, KY
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL + Live

70 MW hybrid in Fleming, KY · In queue since March 2022 · Proposed COD June 2027

70 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 3m

In Study38%
Queue EntryMar 11, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-10

Project Details

State

KY

County

Fleming

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Goddard - Flemingsburg 138 kV

Data Source

LBNL + Live

No news available for this project.