— Project Summary

Queue ID
PJM-AH2-382
Capacity
75 MW
Technology
Solar+Battery
Status
active
Location
Wythe, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL + Live

75 MW hybrid in Wythe, VA · In queue since March 2022 · Proposed COD June 2027

75 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 3m

In Study38%
Queue EntryMar 11, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

VA

County

Wythe

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Wythe _x0013_ Mount Airy 138 kV

Data Source

LBNL + Live