— Project Summary

Queue ID
PJM-AH2-379
Capacity
28.3 MW
Technology
Solar
Status
active
Location
Worcester, MD
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

28.3 MW generation in Worcester, MD · In queue since March 2022 · Proposed COD March 2026

28.3 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4 years

Schedule

1 months past proposed COD

In Study38%
Queue EntryMar 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-01

Project Details

State

MD

County

Worcester

Region

PJM

Developer

Utility

DPL

Entity

PJM

Point of Interconnection

Sign Post - Stockton 69 kV

Data Source

LBNL + Live

No news available for this project.