BetaActiveSolarPJMLBNL + Live
17.816 MW generation in Caroline, MD · In queue since March 2022 · Proposed COD November 2023
17.816 MW
Capacity
1
Components
Solar
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 8m
Schedule
29 months past proposed COD
In Study38%
Queue EntryMar 10, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-11-15
Project Details
State
MD
County
Caroline
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Church - Oil City 138 kV III
Data Source
LBNL + Live
No news available for this project.