BetaActiveSolarPJMLBNL + Live
1,000 MW generation in KY · In queue since March 2022 · Proposed COD December 2028
1,000 MW
Capacity
1
Components
Solar
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 9m
In Study38%
Queue EntryMar 10, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
KY
County
—
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Jefferson - Hanging Rock 765 kV
Data Source
LBNL + Live
No news available for this project.