— Project Summary

Queue ID
PJM-AH2-351
Capacity
1000 MW
Technology
Solar
Status
active
Location
KY
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

1,000 MW generation in KY · In queue since March 2022 · Proposed COD December 2027

1,000 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 9m

In Study38%
Queue EntryMar 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

KY

County

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Jefferson - Hanging Rock 765 kV

Data Source

LBNL + Live

No news available for this project.